Project Details
Location
Value in SR
Client
Period
Type
Consultant

Project Description
Scope of work includes Engineering, Design, Supply, Testing and Commissioning eight (8) new GTG units, each of 60 MW along with related auxiliaries and Balance of Plant on a Lump sum Turnkey Basis.
Scope of Work
Mechanical:

  • 8 x 60 MW GTG including generator, exhaust system, inlet air filter system, and associated auxiliaries.
  • Indoor low speed 4MW black start diesel generator unit
  • Compressed Air System
  • Fire Station and Fire Detection & Protection System
  • Raw Water Station, R.O. Treatment Plant, Demin Water plant including Storage and Distribution Systems
  • Crude Oil treatment plant with capacity of 400 m3/hr
  • Crude & distillate fuel oil forwarding system
  • HVAC system
  • Piping System

Electrical:

  • 6 x 220 MVA GSU Transformers
  • 4 x 30 MVA UAT Transformers
  • Generator Circuit Breaker
  • MV Black Start Switchgear & associated Transformer
  • Metalclad Switchgear MV
  • MV/LV BOP Transformers
  • 132 KV XLPE Power Cables
  • LV Bus Duct System
  • Grounding & Lighting Protection
  • Transformer & Generator Condition Monitoring
  • DC power supply including batteries & UPS
  • Modification at Substation 8801 & 8825
  • Interconnection of the new project system with the existing system
  • Instrumentation & Control works
  • DCS System
  • Security System

Civil:

  • Site clearance and Site Preparation
  • Foundations for GTG, Exhaust Stack, GUT, BSDG
  • Irrigation and Drainage System, Piping Distribution, Plant Drainage.
  • Turbine buildings, Control Room, Battery Room, Fuel Pump Room, Switchgear Room, Gatehouse, Security Fence, etc.
Qassim, KSA
1429 Millions
SEC-COA
Nov 7, 10 to Oct 8, 12
ACTIVE POWER & TRANSMISSION