Project Description


Scope of Work

The scope of work of this Project includes Engineering, Supply, Installation, Testing and Commissioning of 110 KV Substation as follows:

  • 6 Bays 110 KV GIS
  • 3 Nos. 40 MVA Transformers
  • 13.8 KV Switchgear
  • Protection & Control System
  • Civil Works
  • Electromechanical Works
  • Fire Fighting
  • Civil/Building
  • GIS/Switchgear
    • Building 1,000 m2
    • Medium Voltage/Control Building}
Safa Saudi Arabia
27 Millions
SEC-WRB
19/08/02 To 18/02/04
POWER GENERATION & TRANSMISSION
AMCDE