Project Details
Location
Value in SR
Client
Period
Type
Consultant
Project Description
The scope of work of this project is to extend the existing power plant by an additional 300 MW. This is being accompanied by adding 6x50 M GE model PG711EA simple cycle gas turbine with all associated equipment, controls and interface with existing plant. The new turbine will be located in a new building.
Scope of Work
- Detailed engineering of the whole plant.
- Installation and erection of mechanical & electrical equipment.
- Installation of gas turbines.
- Procurement & engineering for balance of plant.
- Civil / Buildings
- Fuel Management Building
- Switchgear Building
- GT Building
Riyadh, Saudi Arabia
90 Millions
SAMGE/AL-SEIF
May 1994 To Sept. 1995
POWER GENERATION & TRANSMISSION
By the Client