Riyadh Power Plant No.9 Combined Cycle (5,980 MW)

The combined cycle plant (PP9) has been built on a site of 3.2 million square meter about 54km east of Riyadh. This construction, together with an expansion of the existing PP 9 facility, made Riyadh the largest crude oil-fired power plant in the world. Arabian Bemco Contracting Company was awarded the project by SEC. Works Started in 1995,

Riyadh Power Plant No.10 Combined Cyle (4,600 MW)

On June 30, 2008 Arabian Bemco was awarded a S.R 11 billion (USD 3 billion) contract with SEC for a turnkey supply and installationof a 2,600 MW power geneartion plant (PP10) built on an area of 5 million square meter outside the capital of Saudi Arabia, Riyadh.This is a Greenfield project that will initially install 36 GTG simple cycle base loaded gas turbines on

Qurayyah Combined Cycle Project (4,600 MW)

On June 11, 2007, Arabian Bemco was awarded a SR 2.1 billion (USD 570 Million) contract with SEC to build the 2,500 MW Qurrayah Open Cycle Power Plant in the Eastern Province of KSA. Under the engineering, civil construction and mechanical erection package, Arabian Bemco will install gas-fired turbines at the plant supplied by

Riyadh Power Plant No.12 Combined Cycle (2,175 MW)

On May 16, 2012, Arabian Bemco signed a S.R 4.7 billion contract (USD 1.3 billion) with the Saudi Electricity Company to build a Grass Root Combined Cycle Power Plant in Riyadh, Saudi Arabia. The plant is located 100 KM West of Riyadh City. Once completed, the new grass root combined cycle power plant (PP12) will produce


The local Arabian Bemco Contracting on 6 May signed a contract with Germany’s Siemens to carry out erection works at the kingdom’s

The local Arabian Bemco Contracting on 6 May signed a contract with Germany’s Siemens to carry out erection works at the kingdom’s

first independent power project (IPP) in Jubail, being promoted by Saudi Petrochemical Company (Sadaf).

Under the six-month contract, initially valued at about SR 12 million ($3.2 million), Bemco will erect the plant’s two Siemens W501D5A turbines, which will produce about 250 MW of power, and carry out electrical installation works.

The project is due to be completed in the second quarter of 2005. The project company is Jubail Energy Company.